Soluna Unveils 48MW Green Bitcoin Mining Expansion, Increasing Capacity by 60%

0
56
Soluna Unveils 48MW Green Bitcoin Mining Expansion, Increasing Capacity by 60%

Soluna Holdings (NASDAQ: SLNH) has commenced the initial energizing and phased commissioning of Project Dorothy 2, a major enhancement of its Bitcoin hosting capabilities. This initiative will contribute 48 MW of renewable energy capacity through three phases (18, 14, and 16 MW), increasing Soluna’s total capacity to 123 MW.

The facility is connected to a 150 MW wind farm located in Silverton, Texas, and is expected to be fully operational by Q4 2025, with the first 18 MW phase set to ramp up in Q2 2025. Project Dorothy 2 is forecasted to generate annual revenues ranging from $19-25 million and will have a hashrate capacity of 2.2 EH/s.

This expansion builds on the achievements of Project Dorothy 1, illustrating Soluna’s scalable strategy towards curtailment solutions and environmentally sustainable computing. The facility is engineered to integrate with renewable energy sources, optimizing the use of clean energy while efficiently managing Bitcoin mining operations with a lower environmental footprint.

Soluna Holdings (NASDAQ: SLNH) ha avviato l’energizzazione iniziale e la messa in servizio graduale del Progetto Dorothy 2, un’importante espansione della sua capacità di hosting per Bitcoin. Il progetto aggiungerà 48 MW di capacità alimentata da fonti rinnovabili attraverso tre fasi (18, 14 e 16 MW), portando la capacità totale di Soluna a 123 MW.

La struttura, collegata a un parco eolico da 150 MW a Silverton, Texas, sarà completamente operativa entro il quarto trimestre del 2025. La prima fase da 18 MW sarà avviata nel secondo trimestre del 2025. Si prevede che il Progetto Dorothy 2 genererà entrate annuali comprese tra $19-25 milioni con una capacità di hashrate di 2.2 EH/s.

L’espansione si basa sul successo del Progetto Dorothy 1, dimostrando l’approccio scalabile di Soluna alle soluzioni di limitazione e al computing sostenibile. La struttura è progettata per integrarsi con fonti di energia rinnovabile e ottimizzare l’uso dell’energia pulita, supportando al contempo i carichi di lavoro di mining di Bitcoin con un impatto ambientale ridotto.

Soluna Holdings (NASDAQ: SLNH) ha comenzado la energización inicial y la puesta en marcha por fases del Proyecto Dorothy 2, una expansión significativa de su capacidad de alojamiento de Bitcoin. El proyecto añadirá 48 MW de capacidad alimentada por energía renovable a través de tres fases (18, 14 y 16 MW), llevando la capacidad total de Soluna a 123 MW.

La instalación, conectada a un parque eólico de 150 MW en Silverton, Texas, estará completamente operativa para el cuarto trimestre de 2025. La primera fase de 18 MW se pondrá en marcha en el segundo trimestre de 2025. Se espera que el Proyecto Dorothy 2 genere ingresos anuales de entre $19-25 millones con una capacidad de hashrate de 2.2 EH/s.

La expansión se basa en el éxito del Proyecto Dorothy 1, demostrando el enfoque escalable de Soluna hacia soluciones de limitación y computación sostenible. La instalación está diseñada para integrarse con fuentes de energía renovable y optimizar el uso de energía limpia, al mismo tiempo que apoya las cargas de trabajo de minería de Bitcoin con un impacto ambiental reducido.

솔루나 홀딩스 (NASDAQ: SLNH)는 비트코인 호스팅 용량의 중요한 확장인 프로젝트 도로시 2의 초기 전력 공급 및 단계적 시운전을 시작했습니다. 이 프로젝트는 세 가지 단계(18, 14, 16 MW)를 통해 48 MW의 재생 가능 전력 용량을 추가하여 솔루나의 총 용량을 123 MW로 늘릴 것입니다.

이 시설은 텍사스 실버턴에 위치한 150 MW 풍력 발전소에 연결되어 있으며, 2025년 4분기까지 완전히 운영될 예정입니다. 첫 번째 18 MW 단계는 2025년 2분기에 가동될 것입니다. 프로젝트 도로시 2는 연간 $19-25 백만의 수익을 생성할 것으로 예상되며, 해시레이트 용량은 2.2 EH/s입니다.

이번 확장은 프로젝트 도로시 1의 성공을 기반으로 하며, 솔루나의 제한 솔루션 및 지속 가능한 컴퓨팅에 대한 확장 가능한 접근 방식을 보여줍니다. 이 시설은 재생 가능 에너지원과 통합되도록 설계되었으며, 청정 에너지 사용을 최적화하면서 비트코인 채굴 작업의 환경 영향을 줄이는 데 기여합니다.

Soluna Holdings (NASDAQ: SLNH) a commencé l’alimentation initiale et la mise en service progressive du Projet Dorothy 2, une expansion significative de sa capacité d’hébergement Bitcoin. Le projet ajoutera 48 MW de capacité alimentée par des énergies renouvelables à travers trois phases (18, 14 et 16 MW), portant la capacité totale de Soluna à 123 MW.

La structure, connectée à un parc éolien de 150 MW à Silverton, Texas, sera entièrement opérationnelle d’ici le quatrième trimestre 2025. La première phase de 18 MW sera mise en service au deuxième trimestre 2025. On s’attend à ce que le Projet Dorothy 2 génère des revenus annuels compris entre $19-25 millions avec une capacité de hashrate de 2,2 EH/s.

L’expansion s’appuie sur le succès du Projet Dorothy 1, démontrant l’approche évolutive de Soluna en matière de solutions de limitation et d’informatique durable. La structure est conçue pour s’intégrer aux sources d’énergie renouvelable et optimiser l’utilisation de l’énergie propre tout en soutenant les charges de travail de minage de Bitcoin avec un impact environnemental réduit.

Soluna Holdings (NASDAQ: SLNH) hat mit der initialen Stromversorgung und der schrittweisen Inbetriebnahme des Projekts Dorothy 2 begonnen, einer bedeutenden Erweiterung seiner Bitcoin-Hosting-Kapazität. Das Projekt wird 48 MW an erneuerbarer Kapazität durch drei Phasen (18, 14 und 16 MW) hinzufügen und die Gesamtkapazität von Soluna auf 123 MW erhöhen.

Die Anlage, die mit einem 150 MW Windpark in Silverton, Texas, verbunden ist, wird bis zum vierten Quartal 2025 vollständig betriebsbereit sein. Die erste Phase mit 18 MW wird im zweiten Quartal 2025 hochgefahren. Es wird erwartet, dass das Projekt Dorothy 2 jährliche Einnahmen von $19-25 Millionen mit einer Hashrate-Kapazität von 2,2 EH/s generiert.

Die Erweiterung baut auf dem Erfolg des Projekts Dorothy 1 auf und zeigt Solunas skalierbaren Ansatz für Drosselungslösungen und nachhaltiges Computing. Die Anlage ist darauf ausgelegt, sich mit erneuerbaren Energiequellen zu integrieren und die Nutzung sauberer Energie zu optimieren, während sie gleichzeitig die Bitcoin-Mining-Lasten mit reduziertem Umwelteinfluss unterstützt.

Positive

  • Significant capacity expansion adding 48 MW of Bitcoin hosting capability
  • Projected annual revenue of $19-25 million from Project Dorothy 2
  • Strategic integration with 150 MW wind farm for sustainable energy use
  • Substantial hashrate capacity of 2.2 EH/s
  • Phased implementation lowers operational risks

Negative

  • Extended completion schedule stretches to Q4 2025
  • Complete revenue realization postponed until full project deployment

Insights

Soluna’s activation of Project Dorothy 2 signifies a considerable capacity enhancement that boosts the company’s Bitcoin hosting abilities by 60% to 123 MW. The phased methodology—initiating with 18 MW in Q2 2025 and culminating with 48 MW by Q4 2025—illustrates a deliberate execution of their growth strategy.

Moreover, the anticipated annual revenue of $19-$25 million from this single facility is notably significant in relation to Soluna’s current $10.7 million market capitalization. This disparity between revenue and valuation underscores the potential substantial influence this expansion could exert on the company’s financial trajectory.

The strategic collaboration with a 150 MW wind farm aligns seamlessly with their core mission of leveraging curtailed renewable energy for computational applications. This approach addresses dual challenges: effectively utilizing otherwise wasted renewable energy while providing a sustainable foundation for energy-intensive Bitcoin operations.

Soluna’s capacity to cost-effectively scale to substantial sizes (100 MW+) reinforces their operational model. With a hashrate capacity of 2.2 EH/s, Project Dorothy 2 positions Soluna as a more substantial contender in delivering renewable-powered Bitcoin hosting infrastructure, especially at a time when sustainable mining solutions are in greater demand.

Initial phase powered up and ramping; completion expected by Q4 2025.

ALBANY, N.Y.–(BUSINESS WIRE)– Soluna Holdings, Inc. (“Soluna” or the “Company”), (NASDAQ: SLNH), a developer of green data centers for AI and other computing-intensive tasks, has received approval from ERCOT and successfully commenced the initial energization and gradual commissioning of Project Dorothy 2, which marks a significant enhancement of its Bitcoin hosting capabilities.

Soluna Powers Up Project Dorothy 2

The activation of Project Dorothy 2 represents the next step in Soluna’s flagship Texas-based data center, designed for seamless integration with renewable energy sources. The initial energization of the first 18 MW will occur in Q2 2025, with the remaining two phases totaling 30 MW completed by Q4 2025.

Summary Facts on Project Dorothy 2:

Total Size: 48 MW
Phases: 3 phases at 18, 14, and 16 MW each
Date of Initial Energization: Q1 2025
Anticipated Annual Revenue: $19$25m
Estimated Date of Completion: Q4 2025
Revenue source: Bitcoin Hosting
Hashrate Capacity: 2.2 EH/s
Primary power source: Wind
Location: Silverton, Texas

The facility links to a 150 MW wind farm, offering a scalable solution for curtailment reduction and optimized clean energy utilization. This new phase enhances computing capacity, solidifying Soluna’s dedication to powering high-performance computing sustainably.

John Belizaire, CEO of Soluna, stated, “The activation of Project Dorothy 2 builds on the success of Project Dorothy 1, showing how Soluna’s methods for curtailment solutions and sustainable computing can be effectively scaled.” He added, “As we enhance our Bitcoin hosting capacity, we continue to draw in the industry’s leading Hyperscale miners with our premium service model known as Relentless Stewardship.”

Key Features of Project Dorothy 2:

  • Enhanced 48 MW of renewable-powered Bitcoin hosting increases Soluna’s total capacity to 123 MW.
  • Strategic cooperation with local energy infrastructure to minimize curtailment.
  • Optimized efficiency for supporting Bitcoin mining operations with reduced environmental impact.
  • Demonstrates the ability to scale data center facilities cost-effectively and efficiently to at least 100 MW+

Soluna upholds a tradition of naming its data centers after pioneering women scientists who spearheaded significant innovations. Project Dorothy is named in honor of Dorothy Vaughan, an African American mathematician and “human computer” who contributed to the National Advisory Committee for Aeronautics and NASA in 1939, embodying excellence in computing and innovation.

For more information about Project Dorothy 2 and Soluna’s mission, visit solunacomputing.com

Safe Harbor Statement

This announcement includes forward-looking statements. These statements are made in accordance with the “safe harbor” provisions of the U.S. Private Securities Litigation Reform Act of 1995. These forward-looking statements encompass all assertions, except for historical facts, concerning our current perspectives and assumptions regarding future occurrences about our business, our expectations regarding anticipated annual revenue and the energization of Project Dorothy 2, as well as our ability to complete the energization of Project Dorothy 2 according to the projected schedule or at all, and other predictive statements. Forward-looking statements can be identified by terminology such as “will,” “expects,” “anticipates,” “future,” “intends,” “plans,” “believes,” “estimates,” “confident,” and similar expressions. Soluna Holdings, Inc. may also provide written or oral forward-looking statements in its periodic reports to the U.S. Securities and Exchange Commission, in its annual shareholder report, press releases, and other written materials, and in oral statements made by its officers, directors, or employees to third parties. Statements that are not historical facts, including but not limited to comments about Soluna’s beliefs and expectations, are forward-looking statements. Forward-looking statements carry inherent risks and uncertainties; further information regarding these can be found in the company’s filings with the Securities and Exchange Commission. All information provided in this press release is as of the date of the announcement, and Soluna Holdings, Inc. assumes no obligation to update such information, except as required by applicable law.

About Soluna Holdings, Inc (Nasdaq: SLNH)

Soluna’s mission is to harness renewable energy as a global powerhouse, utilizing computing as a catalyst. The company designs, develops, and operates digital infrastructure that transforms surplus renewable energy into global computing resources. Soluna’s innovative data centers are strategically located near wind, solar, or hydroelectric power plants to facilitate high-performance computing applications such as Bitcoin Mining, Generative AI, and other compute-heavy tasks. Soluna’s proprietary software, MaestroOS(™), assists in energizing a greener power grid while delivering cost-effective and sustainable computing solutions, leading to superior returns. To learn more, visit solunacomputing.com and follow us on:

LinkedIn: https://www.linkedin.com/company/solunaholdings/
X (formerly Twitter): x.com/solunaholdings
YouTube: youtube.com/c/solunacomputing
Newsletter: bit.ly/solunasubscribe
Resource Center: solunacomputing.com/resources

Cybele Ramirez
Director, Marketing
Soluna Holdings, Inc.
ir@soluna.io

Source: Soluna Holdings, Inc.

FAQ

What is the expected annual revenue for Soluna’s Project Dorothy 2 (SLNH)?

Project Dorothy 2 is expected to generate annual revenue between $19-25 million.

When will Soluna’s Project Dorothy 2 (SLNH) be fully operational?

The project is slated for completion in Q4 2025, with the first 18 MW phase ramping up in Q2 2025.

What is the total power capacity of Project Dorothy 2 and how is it phased?

Project Dorothy 2 has a total capacity of 48 MW, divided into three phases of 18 MW, 14 MW, and 16 MW.

How much will Project Dorothy 2 increase Soluna’s (SLNH) total Bitcoin hosting capacity?

Project Dorothy 2 will raise Soluna’s total Bitcoin hosting capacity to 123 MW, representing a 60% increase.

What is the hashrate capacity of Soluna’s Project Dorothy 2 (SLNH)?

Project Dorothy 2 boasts a hashrate capacity of 2.2 EH/s.